![](http://leebcorservices.com/cmsData/JOC-projects/1523302618/1523302618_0/1523302618_0.jpg)
![](http://leebcorservices.com/cmsData/JOC-projects/1523302618/1523302618_1/1523302618_1.jpg)
Building 10500, HVAC Repair
Fort Lee JOC
$2.7 Million
Contract Number W911SF-14-D-0010 TO 0033
This purpose of this task order was to provide modifications to the existing HVAC system to create appropriate climatic conditions throughout the 159,000-square-foot building. This included the addition of return air fans, VAV boxes for zoning issues, controls modifications and a retro commissioning of the entire building HVAC systems to correct the building over pressurization issues.